Following quiz provides Multiple Choice Questions (MCQs) related to SAP PP. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.

Questions and Answers

Q 1 - Which of the following Transaction code can be used to check PP tables in SAP ECC system?

A - SE16

B - SE18

C - SE20

D - SE22

Answer : A

Q 2 - When you create a Material BOM without a Plant is known as?

A - Reference BOM

B - Master BOM

C - Group BOM

D - Master group

Answer : C

Q 3 - Which of the following T-code can be used to change Routing in PP?

A - CA01

B - CA02

C - CA03

D - CA04

Answer : B

Q 4 - SAP Production Planning is integrated with which of the following modules?

A - Material Management

B - Sales and Distribution

C - Controlling

D - SAP QM

E - All of the above

Answer : E

Q 5 - Long Term Planning is not actual run but is used to see if all capacity requirement can be fulfilled and you can also transfer simulative area to operative area if requirements are fulfilled?

A - True

B - False

Answer : A

Explanation

Long term planning in SAP PP is used to check future demands at all Bill of Material level. You can check the current capacity and vendor ability to provide the material in required time period.

This is not actual run but is used to see if all capacity requirement can be fulfilled and you can also transfer simulative area to operative area if requirements are fulfilled.

Q 6 - Which of the following Transaction code is used to display Production Lot?

A - MDL5

B - MDL3

C - MDL1

D - MEL1

Answer : B

Q 7 - Simulative planning is performed only for long duration and it is not performed for short term and when there is no time restriction?

A - True

B - False

Answer : B

Answer : C

Explanation

Good receipt is performed when material is produced as per Production order and goods is placed at storage location. The stock quantity is increased and movement type 101 is entered.

Q 9 - Which of the following report is used to collect information about hierarchy of work center of a shift?

A - Shift Transfer Report

B - Shift Report

C - Shift Work center Report

D - None of these

Answer : B

Q 10 - Long term planning is almost similar to Material requirement planning in simulate version to predict the production plan as per future requirements?

A - True

B - False