SAP SCM Online Quiz
Following quiz provides Multiple Choice Questions (MCQs) related to SAP SCM. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.
Answer : D
Explanation
SAP Supply Chain Management is one of the key module in SAP ERP and controls Production Planning, business forecasting and demand planning, and helps the organization to manage their supply chain process in a dynamic environment.
Q 2 - When you use Planning strategy 10, which of the following is correct?
A - Only PIR quantity is considered for MRP run & PIR requirement type is VSF.
B - Sales order are completely ignored.
C - For MRP run maximum of 2 PIR and Sales order can be considered
Answer : A
Explanation
When you use Planning strategy 10, only PIR quantity is considered for MRP run and sales order are completely ignored. In this PIR requirement type LSF and is reduced when you deliver stock to customer.
Q 3 - Which of the following is/are benefits of Supply Chain Management process?
B - To effectively manage forecasting and handling sudden changes in demand and supply process.
C - To effectively use Net Fixed assets NFA like plants and equipment.
Answer : E
Q 4 - Which of the following process includes generation of static report that contains planning run material wise and it displays time of MRP run at the top?
Answer : B
Explanation
MRP List is used to generate static report that contains planning run material wise and it displays time of MRP run at the top.
Q 5 - In SAP SCM, which of the following master data is used to define sequence of activities performed at work center?
Answer : D
Explanation
Routing defines sequence of activities performed at work center. Routing plays in important role in calculating production cost, machine time and labor time.
Q 6 - Which of the following represents the active model and the active planning version?
A - model 000 and planning version 000
B - model 111 and planning version 111
Answer : A
Explanation
Active model and the active planning version- model 000 and planning version 000 respectively.
Q 7 - Which of the following is not a valid PDS usage type?
A - PDS for Production and Detailed Planning
Answer : E
Q 8 - Which of the following doesn’t affect Supply Chain process?
Answer : D
Q 9 - After MRP run, which of the following gets created in Planning?